Connecting Two Large Power Utilities
Power Plant Project
Power Plant and Transmission Line
80 MW Windfarm
200 MW Windfarm
Switchyard
Rural Distribution Substation
|
Switchyard
115 kV Switchyard
Project Description:
- Four 115 kV circuit breaker ring bus
- Configured for future breaker and a half
- Four transmission line terminals
|
|
Peak Power Scope: |
Complete substation engineering including
- equipment layout
- bus system design
- structural steel design
- foundation design
- cable trench and conduit
- grounding system design
- control building structural design
- control building electrical design
- relaying
- SCADA design
- wiring design
|
|
|